add procedure for 'idea approved' label
This commit is contained in:
parent
89d3cc5a47
commit
521cca1840
@ -77,10 +77,18 @@ Items on the board progress through the following states:
|
||||
- [most popular issues](https://github.com/NixOS/nix/issues?q=is%3Aissue+is%3Aopen+sort%3Areactions-%2B1-desc)
|
||||
|
||||
Team members can also add pull requests or issues they would like the whole team to consider.
|
||||
|
||||
If there is disagreement on the general idea behind an issue or pull request, it is moved to _To discuss_, otherwise to _In review_.
|
||||
|
||||
To ensure process quality and reliability, all non-trivial pull requests must be triaged before merging.
|
||||
|
||||
If there is disagreement on the general idea behind an issue or pull request, it is moved to _To discuss_.
|
||||
Otherwise, the issue or pull request in questions get the label [`idea approved`](https://github.com/NixOS/nix/labels/idea%20approved).
|
||||
For issues this means that an implementation is welcome and will be prioritised for review.
|
||||
For pull requests this means that:
|
||||
- Unfinished work is encouraged to be continued.
|
||||
- A reviewer is assigned to take responsibility for getting the pull request merged.
|
||||
The item is moved to the _Assigned_ column.
|
||||
- If needed, the team can decide to do a collarorative review.
|
||||
Then the item is moved to the _In review_ column, and review session is scheduled.
|
||||
|
||||
What constitutes a trivial pull request is up to maintainers' judgement.
|
||||
|
||||
- To discuss
|
||||
@ -110,12 +118,12 @@ Items on the board progress through the following states:
|
||||
|
||||
When the overall direction is agreed upon, even when further changes are required, the pull request is assigned to one team member.
|
||||
|
||||
- Assigned for merging
|
||||
- Assigned
|
||||
|
||||
One team member is assigned to each of these pull requests.
|
||||
They will communicate with the authors, and make the final approval once all remaining issues are addressed.
|
||||
|
||||
If more substantive issues arise, the assignee can move the pull request back to _To discuss_ to involve the team again.
|
||||
If more substantive issues arise, the assignee can move the pull request back to _To discuss_ or _In review_ to involve the team again.
|
||||
|
||||
The process is illustrated in the following diagram:
|
||||
|
||||
|